Question 1 Figure Q1a shows the cross section through a site at which it is proposed to lower, for 8 months, the groundw

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Question 1 Figure Q1a shows the cross section through a site at which it is proposed to lower, for 8 months, the groundw

Post by answerhappygod »

Question 1 Figure Q1a Shows The Cross Section Through A Site At Which It Is Proposed To Lower For 8 Months The Groundw 1
Question 1 Figure Q1a Shows The Cross Section Through A Site At Which It Is Proposed To Lower For 8 Months The Groundw 1 (39.88 KiB) Viewed 31 times
Question 1 Figure Q1a Shows The Cross Section Through A Site At Which It Is Proposed To Lower For 8 Months The Groundw 2
Question 1 Figure Q1a Shows The Cross Section Through A Site At Which It Is Proposed To Lower For 8 Months The Groundw 2 (33.72 KiB) Viewed 31 times
Question 1 Figure Q1a shows the cross section through a site at which it is proposed to lower, for 8 months, the groundwater level by 2m as indicated. Figures Q1b and 1c show the results of an oedometer test carried out on a sample of the clay strata. a) Calculate the change in effective stress in the centre of the clay strata due to the lowering of the ground water. 10 marks b) Calculate the magnitude of the settlement caused by consolidation due to the change in stress. 15 marks c) How much of this settlement will be complete after 8months? 15 marks Depth (m) 0 # 1 Original GWL Yunsat = 19kN/m ..Yot - 20kN/m --Final GWL Sand 3 4 Clay Ysat = 18kN/m 10- Sand and Gravel Figure Q1a

20 19.8 19.6 1 19.4 Height of sample (mm) 19.2 19 18.8 18.6 18.4 10 100 1000 Effective vertical stress (kPa) Figure Q1b 18 17.5 17 Height of sample (mm) 16.5 16 15.5 0 0 1 2 2 3 4 5 on 00 10 11 12 13 14 15 6 Square root of time (mins)