During 2010, Tracer Ltd decided to construct a portable sales kiosk for the promotion and marketing of the company's pro
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
During 2010, Tracer Ltd decided to construct a portable sales kiosk for the promotion and marketing of the company's pro
company's products. The following costs were incurred £ Purchase of materials (before deducting trade discount of 5% 30,000 Labour costs 25,000 Correction of design error 2,000 Marketing costs associated with promotion of products incurred during construction 1,200 incurred after completing of construction 1,500 Safety check 1,300 Interest costs incurred during construction 3,000 Present value cost at 31 December 2010 of dismantling kiosk 1,000 Calculate how much should be capitalised as the construction cost of the sales kiosk.