The R&D department is planning to bid on a large project for the development of a new communication system for commercia

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

The R&D department is planning to bid on a large project for the development of a new communication system for commercia

Post by answerhappygod »

The R D Department Is Planning To Bid On A Large Project For The Development Of A New Communication System For Commercia 1
The R D Department Is Planning To Bid On A Large Project For The Development Of A New Communication System For Commercia 1 (11.15 KiB) Viewed 26 times
The R D Department Is Planning To Bid On A Large Project For The Development Of A New Communication System For Commercia 2
The R D Department Is Planning To Bid On A Large Project For The Development Of A New Communication System For Commercia 2 (26.35 KiB) Viewed 26 times
The R D Department Is Planning To Bid On A Large Project For The Development Of A New Communication System For Commercia 3
The R D Department Is Planning To Bid On A Large Project For The Development Of A New Communication System For Commercia 3 (15.35 KiB) Viewed 26 times
The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required: ACTIVITY IMMEDIATE PREDECESSOR ABCDEFGIH А IAAABUDOW C, D D, F E, G, H TIME (WEEKS) 3 WwNG GAAN W 2 4 4 6 6 Nm m 2 3 3
b. What is the critical path? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) ? A-C-F-G-I ? A-B-E-I ? A-D-H-I ? A-D-F-G-I c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) Пв ? C ? D ? G
d-1. What is the new critical path? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) ? A-C-F-G-I ? A-D-H-I ? A-B-E-I ? A-D-F-G-I d-2. What is the earliest completion time for the new critical path? Completion time weeks