- A If The Market Demand 600 H What Is Active Bottle Neck B If The Market Demand 80 H What Is The Constraint C If The 1 (50.19 KiB) Viewed 32 times
a)If the market demand=600/h, What is active bottle neck b)If the market demand=80/h, What is the constraint? c) If the
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
a)If the market demand=600/h, What is active bottle neck b)If the market demand=80/h, What is the constraint? c) If the
a)If the market demand=600/h, What is active bottle neck b)If the market demand=80/h, What is the constraint? c) If the market demand=150/h, What is role of resource D? d)Where is Drum? e)Where is stock buffers? f) Where is the rope? b 6 C 280/h 300 units 280/h 7 hour Lead time 5 h e 160/h 420/h Lead time 3 h Raw Material Ship