Still based on the following diagram, apply the critical pathmethod (CPM). The number in each box refers to the duration of thistask. Which of the following is the free flow ofTask D?
note: I need solution as soon as possible
Note : Use below textbook.
Notes: Construction Management, 5th Edition
This is the primary textbook
Project Management in the Oil and Gas Industry
A ND 2 B 3 с 4 D 5 2 2 E3 F 1 G 2 3 H 4 2 K NX 2
Still based on the following diagram, apply the critical path method (CPM). The number in each box refers to the duratio
-