Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
-
answerhappygod
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Post
by answerhappygod »
Calculate all activity times of the following CPM network and hence obtain critical path and project duration (in days).Calculate the floats.

- Calculate All Activity Times Of The Following Cpm Network And Hence Obtain Critical Path And Project Duration In Days 1 (27.18 KiB) Viewed 22 times
1 10 10 2 3 25 15 13 4 17 5 12 6 14, 1 7 30 8 16 8 9