- 3 A Sand Layer With A Thickness Of 1 5 M Has Been Determine To Exist For A 450 M Length Of A Levee The Coefficient Of 1 (15.33 KiB) Viewed 47 times
3. A sand layer with a thickness of 1.5 m has been determine to exist for a 450 m length of a levee .The coefficient of
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
3. A sand layer with a thickness of 1.5 m has been determine to exist for a 450 m length of a levee .The coefficient of
3. A sand layer with a thickness of 1.5 m has been determine to exist for a 450 m length of a levee .The coefficient of conductivity or permeability of the sand layer is 3m per day. At the left side of the levee is a river whose water surface elevation is 160 m and at the right side of the levee is a ditch whose water surface elevation is 150 m .The length of the sand layer is 120 m,determine the hydraulic gradient of the sand layer A. 0.0789 B. 0.0833 C. 0.0678 D. 0.0587