d) When there is res 15. Assuming that each activity needs the same type of resource, for the project whose information
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
d) When there is res 15. Assuming that each activity needs the same type of resource, for the project whose information
d) When there is res 15. Assuming that each activity needs the same type of resource, for the project whose information is given in the table; a) What is the resource requirement in the third day? (8p) b) What is the resource requirement in the third day after making the necessary resource smoothing? (8p) Activity Predecessors ABCDEFG === A A A B, C B, D E, F Duration, day 2 5 3 2 3 2 Labour number 2 3 3 4 2 3 3