The three estimated times (in weeks) and immediate predecessors for the activities in a project are given in the followi

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

The three estimated times (in weeks) and immediate predecessors for the activities in a project are given in the followi

Post by answerhappygod »

The three estimated times (in weeks) and immediate predecessors
for the activities in a project are given in the following table.
Assume that the activity times are independent.
Activity
Immediate predecessors
a
m
b
t
ES
EF
LS
LF
SLACK
A
-
9
10
11
B
A
4
10
16
C
A
8
9
10
D
B
5
8
11
E
B, C
10
12
14
F
D
8
10
12
G
D, E
6
7
8
What is the probability that the project will be completed in 42
weeks or less?
74%
92%
68%
67%