- The Texas Department Of Transportation Txdot Is Considering Two Designs For Crash Barriers Along A Reconstructed Porti 1 (42.94 KiB) Viewed 32 times
The Texas Department of Transportation (TxDOT) is considering two designs for crash barriers along a reconstructed porti
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
The Texas Department of Transportation (TxDOT) is considering two designs for crash barriers along a reconstructed porti
The Texas Department of Transportation (TxDOT) is considering two designs for crash barriers along a reconstructed portion of 1-10. Design 2B will cost $3 million to install and $144,000 per year to maintain. Design 4R will cost $3.7 million to install and $55,000 per year to maintain. Determine which design should be selected based on a rate of return analysis if TxDOT uses a MARR of 6% per year and a 20-year project period. The rate of return is %. Design (Click to select) is selected. (Click to select) 4R 2B *******