4. [1.67/20 Points] DETAILS PREVIOUS ANSWERS ASWMSCI15 9.E.018. ASK YOUR TEACHER The manager of the Oak Hills Swimming C
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
4. [1.67/20 Points] DETAILS PREVIOUS ANSWERS ASWMSCI15 9.E.018. ASK YOUR TEACHER The manager of the Oak Hills Swimming C
(a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen This answer has not been graded yet. (b) Develop an activity schedule. (Round your answers to two decimal places.) Latest Start Activity A B C D E F G H 1 Earliest Start 1.16 0.11 x 1.16 x 0.11 X Earliest Finish 1.16 0.44 x 1.16 x 10000 Latest Finish (c) What are the critical activities? (Enter your answers as a comma-separated list.) X — 1.16 0.44 0.44 0.11 0.11 0.11 0.11 0 0.11 What is the expected project completion time (in weeks)? (Round your answer to two decimal places.) 14.16 x weeks Slack x x x X x x x
(c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project completion time (in weeks)? (Round your answer to two decimal places) 14:16 x weeks (4) If the club manager plans to start the project on February 1, calculate the probability the swimming program will be ready by the scheduled May 1 date (13 weeks) based solely on the critical path. (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places.) 000 Should the manager begin planning the swimming program before February 17 (The probability for finishing on schedule should be at least 0.9.) Since the probability that the swimming program will be ready by May 1 is less than 0.9, the manager should Need Help? Poody begin planning before February 1.