Activity P on a project has exactly 4 predecessors A, B, C, and D whose ear days are 20, 12, 38, and 32. (Here "day" mea
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Activity P on a project has exactly 4 predecessors A, B, C, and D whose ear days are 20, 12, 38, and 32. (Here "day" mea
Activity P on a project has exactly 4 predecessors A, B, C, and D whose ear days are 20, 12, 38, and 32. (Here "day" means days after project start.) W early start day of P? 13 38 039 21