QUESTION 2 Table 1 shows activities in Project Z. Based on the information given, determine the following. a) b) c) Acti
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
QUESTION 2 Table 1 shows activities in Project Z. Based on the information given, determine the following. a) b) c) Acti
QUESTION 2 Table 1 shows activities in Project Z. Based on the information given, determine the following. a) b) c) Activity A ii) G B C D E F G iii) H H 1 Draw the AON network diagram. Table 1 Duration 4 Identify the critical path. 6 4 2 5 53 3 5 NG 2 Predecessor None None None Calculate ES, EF, LS, LF and Slack for following activities: i) A B,C B E,D A,C G F,G [20 marks] [3 marks] [5 marks] [5 marks] [5 marks] [2 marks]