A-E are completed and need help with F-K. A. Project A was budgeted at $50,000 and it is 60% complete. Calculate the ear

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

A-E are completed and need help with F-K. A. Project A was budgeted at $50,000 and it is 60% complete. Calculate the ear

Post by answerhappygod »

A-E are completed and need help with F-K.
A. Project A was budgeted at $50,000 and it is 60% complete.Calculate the earned value. EV = 30,000
B. In Project A, 60% of the work is complete, but 80% (of$50,000 worth of work) was supposed to be completed. Calculate theplanned value. PV = 40,000
C. In Project A, 60% of the work is done, 80% was supposed to bedone, but regardless, the project has spent $45,000. What is theactual cost? AC = 45,000
D. Using the above calculated EV, PV, and AC, calculate the costperformance index, and explain if the project is under budget orover budget, and why? CPI = 0.66
E. Using the above calculated EV, PV, and AC, calculate theschedule performance index, and explain if the project is ahead ofschedule or behind schedule, and why? SPI =0.75
F. From the information available in exercise A, what is thebudget at completion value? BAC =
G. Using the above calculated EV, AC, and BAC calculate theestimate at completion value for estimated to complete workperformed at the budgeted rate. EAC =
H. Using the above calculated EV, AC, BAC, and CPI calculate theestimate at completion value for estimated to complete workperformed at the present CPI. EAC =
I. Using the above calculated EV, AC, BAC, CPI, and SPIcalculate the estimate at completion value for estimated tocomplete work considering both SPI and CPI factors: EAC =
J. Using the above calculated EV, AC, BAC, and EAC for exerciseG, calculate the ToComplete Performance Index (based on the EAC).TCPI =
K. Using the above calculated EV, AC, and BAC calculate theTo-Complete Performance Index (based on the BAC). TCP