Question 2 A continuous time study was conducted in a job that contains four elements. The observed time and performance
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Question 2 A continuous time study was conducted in a job that contains four elements. The observed time and performance
Question 2 A continuous time study was conducted in a job that contains four elements. The observed time and performance ratings of 7 cycles are shown below: Use 2 decimal places. Element 1 2 3 4* Rating Factor 92% 88% 112% 115% 1 0.44 1.99 2.83 3.93 *Irregular element performed every 12 cycles 2 0.49 2.2 2.95 3.97 Observations / Cycles (min) 4 5 0.62 0.67 2.98 3.4 3.85 43 4.32 454 b. Compute the standard time for the job. 15.07 3 0.53 2.35 3.15 42 6 0.75 3.9 4.92 4.94 7 4.86 4.4 52 5.15 a. Given a workday allowance of 10% allotted for an 8-hr operation, compute the personal allowance in minutes, given the following additional data: Unavoidable delay = 20 mins; Lunch break 60 mins; Personal allowance 40 minutes 20 points Seved