Draw an activity chart for a machine operator with the following operation. The relevant times are as follows: O A. Plot

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Draw an activity chart for a machine operator with the following operation. The relevant times are as follows: O A. Plot

Post by answerhappygod »

Draw An Activity Chart For A Machine Operator With The Following Operation The Relevant Times Are As Follows O A Plot 1
Draw An Activity Chart For A Machine Operator With The Following Operation The Relevant Times Are As Follows O A Plot 1 (44.81 KiB) Viewed 12 times
Draw An Activity Chart For A Machine Operator With The Following Operation The Relevant Times Are As Follows O A Plot 2
Draw An Activity Chart For A Machine Operator With The Following Operation The Relevant Times Are As Follows O A Plot 2 (78.86 KiB) Viewed 12 times
Draw an activity chart for a machine operator with the following operation. The relevant times are as follows: O A. Plot all required processes and their relevant times on the chart. Choose the correct graph below. Time HERE F1. -3- -4- -6 Operator Time Machine Time Prepare Mill Idle Load Mill Idle Unload Mill F1- 2 5 -6 Mill Operating (Cutting Material) Idle 1 2 -5- Prepare mill for loading (cleaning, oiling, and so on) Load mill 6 Mill operating (cutting material) Unload mill Q Q OB. 0.50 min 1.75 min 2.25 min 0.75 min Time 1 2- 3 -5 6 Operator Prepare Mill Load Mill Idle Unload Mill Time 1 2 -3- -5 2 -6- Machine Time Idle Mill Operating (Cutting Material) Idle - 1 2 5 -6- Q Q
O C. Time Operator Time Machine Time Prepare Mill 1 Load Mill 1 Idle 2 18 3 Mill 3 Idle Operating (Cutting 4 Material) 4 Unload Mill Idle 5 6 1 2 3 4 5 6 LO N 5 CO O D. Time 1 2 3 4 5 6 Operator Prepare Mill Load Mill Idle Unload Mill Time 1 2 3 Mill Operating (Cutting 4 Material) LO 5 Machine Time 6 Idle Idle I I - 2 3 4 5 6 N
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!