- The Following Table Represents A Plan For A Project Times Days Job No 1 23456789gh 10 11 Predecessor Job 5 1 1 1 2 1 (45 KiB) Viewed 11 times
The following table represents a plan for a project: TIMES (DAYS) JOB NO. 1 23456789GH 10 11 PREDECESSOR JOB (5) 1 1 1 2
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
The following table represents a plan for a project: TIMES (DAYS) JOB NO. 1 23456789GH 10 11 PREDECESSOR JOB (5) 1 1 1 2
The following table represents a plan for a project: TIMES (DAYS) JOB NO. 1 23456789GH 10 11 PREDECESSOR JOB (5) 1 1 1 2 3 4 in 37 5, 6 8 7 9, 10 01-3-6-8-9-11 01-2-5-8-9-11 O1-4-7-10-11 b. Indicate the critical path. 0 2 Expected completion time 43LHANNMI 12 1 1 1 2 2 5 E3NS4 m 5 b 4 3 4 7 22 12 4 11 3 2 8 4 5 3 9 4 12 6258 c. What is the expected completion time for the project? (Do not round intermediate ca places.)