A company must perform a maintenance project consisting of eight activities. The activities, their predecessors, and the
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
A company must perform a maintenance project consisting of eight activities. The activities, their predecessors, and the
company must perform a maintenance project consisting of eight activities. The activities, their predecessors, and their respective time estimates are presented below: Time in Days Activity Designation Break down both machines Setup machine 1 Setup machine 2 Clean machine 1 Clean machine 2 Re-set machine 1 Re-set machine 2 Re-calibrate both machines Final test A B с D E F G H 1 Immediate Predecessor None A A B с E F. G H Using the Single Time Estimate CPM procedure, what is the slack time for activity F? O A. 1 day OB. 2 days O C. 3 days O D.0 days 3 1 2 3 3 4 2 1 2