This is Anita’s work center. Five jobs are waiting forprocessing through two work centers. Their processing time (inminutes) at each work center is contained in the table below. Eachjob requires work center Cici before work center Caca. UseJohnson's rule to sequence these five jobs for minimum totalduration. Show your work in determining the job sequence and afterhow many hours will all jobs be completed?
.
Job
Cici
Caca
R
20
10
S
25
35
T
50
20
U
26
26
V
55
75
This is Anita’s work center. Five jobs are waiting for processing through two work centers. Their processing time (in mi
-