If a firm uses the same weighted average cost of capital for evaluating all projects, which situation(s) will likely occur? 1) The firm will reject good low-risk projects. II) The firm will accept poor high-risk projects. III) The firm will correctly accept projects with average risk. I and III only I, II and III I and II only II and III only