Using The Following Project Information Optimistic Time Estimate Weeks 2 2 5 5 Activity A B C D E F G H 1 J 3 4 4 4 2 M 1 (18.52 KiB) Viewed 36 times
Using The Following Project Information Optimistic Time Estimate Weeks 2 2 5 5 Activity A B C D E F G H 1 J 3 4 4 4 2 M 2 (9.24 KiB) Viewed 36 times
Using the following project information Optimistic Time Estimate(weeks) 2 2.5 5 Activity A B C D E F G H 1 J 3 4 4 4 2 Most Likely Time Estimates (weeks) 6 5 7 5 5 6 8 Pessimistic Time Estimates (weeks) 5 8 7 14 9 6 8 10 3 The critical path is A-C-E-G-I-J. D E F G H 1 J Activity A B C Variance 0.25 0.17 0.25 0.44 2.78 1.36 0.11 0.11 1.00 0.03 Immediate Predecessor(s) none A A B,C B.C D E F G H.I
(a) Calculate the probability that the project will be completed in 31 weeks. (Round your answer to 4 decimal places, eg. 1.7945) Plprojects 31)- (b) Calculate the probability that the project will be completed in 35 weeks. (Round your answer to 4 decimal places, e.g. 1.7945) P(projects 35) -
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!