A contract is under consideration which would require 1,400 hours of direct labour. There is spare capacity of 500 hours
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
A contract is under consideration which would require 1,400 hours of direct labour. There is spare capacity of 500 hours
A contract is under consideration which would require 1,400 hours of direct labour. There is spare capacity of 500 hours of direct labour, due to the cancellation of another order by a customer. The other time would have to be found by asking employees to work in the evenings and at weekends, which would be paid at 50% above the normal hourly rate of R15. Alternatively, the additional hours could be found by switching labour from other work which earns a contribution of R5 per hour. Required: Calculate the relevant cost of direct labour if the contract is accepted and undertaken.