17. A developer has called and asked you to provide a quick budget for a new office building in Washington, DC. He has i
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
17. A developer has called and asked you to provide a quick budget for a new office building in Washington, DC. He has i
Comparable Office Projects Project Location Bid Date Office A DC 11/25/2021 Office B VA 4/18/2021 Office C DC 6/22/2021 Office Gross Area Foundation type Structure Type Skin Materials 265,000 spread ftgs Steel Precast/ 339,000 spread ftgs CIP Concrete 295,000 spread ftgs CIP Concrete Precast/ Punched Windows Yes Chilled Water Ribbon Window All Glass Curtainwall No Green Roof Mechanical System Yes Chilled Water Condenser Water Levels Above Grade Exterior Skin Ratio Core Ratio Elevators 12 34% 12% 5 38% 15% 5 12 34% 12% 7 6 Office Building $/gross sf Structure Exterior Skin Roofing & Waterproofing General Building Finishes Elevators Mechanical and Plumbing Sprinkler Electrical General Conditions Insurance Fee Total Office Building $34.00 $31.00 $3.00 $12.00 $6.50 $28.00 $3.25 $21.00 $8.33 $1.47 $5.20 $153.74 $33.00 $35.00 $4.00 $12.00 $6.25 $22.00 $3.10 $16.00 $7.88 $1.39 $4.92 $145.55 $34.50 $35.00 $3.50 $14.00 $6.25 $26.50 $3.00 $19.00 $8.51 $1.50 $5.31 $157.07