Question 15 Given a risk-adjusted discount rate of 8%, calculate the discounted payback period for the following cash fl
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Question 15 Given a risk-adjusted discount rate of 8%, calculate the discounted payback period for the following cash fl
Question 15 Given a risk-adjusted discount rate of 8%, calculate the discounted payback period for the following cash flow of a project. If the maximum target discounted payback period is 5 years, comment on the financial acceptability of the project. Year o Year 1 Year 2 Year 3 Year 4 Year 5 -9000 2000 2500 2800 3000 3000 A. Accept the project, as the target payback period is 5, which is longer than the adjusted payback period of 3.55. B. Turn down the project, as the adjusted payback period is 5.28, which is longer than the target period of 5 years. C. Accept the project, as the target payback period is 5, which is longer than the adjusted payback period of 3.79. D. Accept the project, as the adjusted payback period is 4.28, which is shorter than the target period of 5 years.