Question 2) Design an Assembly Line to produce 40 units in an 8-hour shift. When the precedence relationships and durati
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Question 2) Design an Assembly Line to produce 40 units in an 8-hour shift. When the precedence relationships and durati
Question 2) Design an Assembly Line to produce 40 units in an 8-hour shift. When the precedence relationships and durations (in minutes) are as given below: Use the largest candidate rule to assign work elements to stations and calculate the line efficiency. Machine Predecessor Duration 1 2 1 3 1 4 1 5 3 6 3,4 7 2 8 5,6 9 4 12 10 7,8,9 Dowowin