QUESTIONS In highway 69/400 bridge project. GFRB rebars procurement is a subtask of parapet railing procurement. True O
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
QUESTIONS In highway 69/400 bridge project. GFRB rebars procurement is a subtask of parapet railing procurement. True O
QUESTIONS In highway 69/400 bridge project. GFRB rebars procurement is a subtask of parapet railing procurement. True O False QUESTION 6 For a girder bridge, abutments provide support for the O a. The ends of the bridge Ob. intermediate sections O c. first pier O d. none of the above --total float are given the highest priority QUESTION 7 In highway 69/400 bridge schedule, activities are ordered to their float. Those with the a higher b. smallest O c. highest O d. none of the above QUESTION 8 What type of falsework is used for construction of a continuous bridge with relatively high elevation? a.standard pipe Ob timber falsework O c heavy-duty pipe d. none of the above