- Problem 10 An Excavation 5m Depth Is Supported By A Sheet Pile The Sheet Pile Is Extended 3 2m Below The Ground And The 1 (90.75 KiB) Viewed 58 times
PROBLEM 10-An excavation 5m depth is supported by a sheet pile. The sheet pile is extended 3.2m below the ground and the
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
PROBLEM 10-An excavation 5m depth is supported by a sheet pile. The sheet pile is extended 3.2m below the ground and the
PROBLEM 10-An excavation 5m depth is supported by a sheet pile. The sheet pile is extended 3.2m below the ground and the water table is at the bottom of the pile. Unit weight of soil is 1.91g/cc. Angle of internal friction is 34°. Which of the following most nearly gives the active force? * O . 178. 3 kN. 168. 3 kN. 158. 3 kN. 148. 3 kN. O NONE OF THE ABOVE