Case 1 Jobs Job-1 Job-2 Job-3 Job-4 Job-5 Stage-1 1,5 1,25 1,75 1,25 1,5 Stage-2 0,25 1,5 0,5 2 2,5 In this case there a
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Case 1 Jobs Job-1 Job-2 Job-3 Job-4 Job-5 Stage-1 1,5 1,25 1,75 1,25 1,5 Stage-2 0,25 1,5 0,5 2 2,5 In this case there a
Case 1 Jobs Job-1 Job-2 Job-3 Job-4 Job-5 Stage-1 1,5 1,25 1,75 1,25 1,5 Stage-2 0,25 1,5 0,5 2 2,5 In this case there are five jobs that each must be done through two stage-1 and stage-2 processes. Determine the order of the job to get the shortest total time!