Examine each segment’s information individually at first. Look at the original budget and the project-to-date actual co

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Examine each segment’s information individually at first. Look at the original budget and the project-to-date actual co

Post by answerhappygod »

Examine each segment’s information individually at first.
Look at the original budget and the project-to-date actual cost
information for the completed months (all values are in thousands
of dollars), then the forecast for the remaining months and the
bottom-line updated FCAC for that segment. For each
individual segment forecast do you feel the total bottom-line FCAC
provided to you may be too conservative (i.e. too high /
too pessimistic), too aggressive (i.e. too low / too optimistic) or
“reasonable and realistic?” Referencing the data,
WHY do you feel that way for each segment?
What follow-up questions do you have based on your
initial look at their summaries of actual results and
forecasts?
E-Street On-Ramp FCAC:
Tenth Avenue Exit FCAC:
Examine Each Segment S Information Individually At First Look At The Original Budget And The Project To Date Actual Co 1
Examine Each Segment S Information Individually At First Look At The Original Budget And The Project To Date Actual Co 1 (174.35 KiB) Viewed 54 times
Updated Forecast Cost At Completion - Thousands of Dollars Garden State E-Street Thunder Road 10th Avenue Exit Parkway On-Ramp Overpass Improvements Thousands Thousands Thousands Baseline Actual Baseline Actual Baseline Actual Calendar Project and Plan and Plan and Month Month Budget Forecast Budget Forecast Budget Forecast July 1 $150 $141 $200 $196 $300 $328 Aug 2 $100 $94 $125 $126 $240 $252 Sep 3 $100 $90 $125 $123 $240 $256 Plan Oct 4 $100 $125 $180 $240 $254 Nov 5 $100 $92 $93 $90 $125 $124 $240 $251 Dec 6 $100 $125 $126 $240 $255 Jan 7 $100 $100 $125 $125 $240 $224 Feb 8 $100 $125 $240 $224 $100 $100 $125 $125 Mar 9 $240 $224 $100 $100 Apr 10 $100 $125 $240 $224 May 11 $100 $100 $125 $125 $125 $125 $1,575 $125 $240 $224 June 12 $240 $224 Total Budget and updated FCAC $100 $1,250 Baseline Plan Budget $100 $1,200 Updated FCAC $125 $1,625 Updated FCAC Baseline Plan Budget $2,940 Baseline Plan Budget $2,940 Updated FCAC