Case Study: Seneca Construction is a non for profit
organization. The organization does different social projects in
Ontario. This year Seneca Constructions is helping restauration
owners to set up for patio dining at a 50% discounted rate. You
have been hired as a team member for one of such projects. We are
meeting the customer this week. Project Manager has assigned you to
create a WBS for Jack and Jill café. A patio set up project will
typically involve:
Phase # 1: Where we meet customers, collect requirements and
covert these requirements into project scope. Phase # 1 is
completed when Seneca Construction and the customer scope statement
of the project.
Phase # 2: Involves getting all design and drawings completed.
It may also have back and forth communication with customer to make
improvements to the drawings. Customer approved drawings are
submitted to the govt. agencies for the construction permits
related to the makeover. The milestone to mark the end of Phase # 2
is to secure approvals and permits.
Phase # 3: Is considered closed when all the work is completed
according to the scope statement. This would involve, site
preparation, site improvements, furniture installation and setting
up al decorations.
Phase # 4 is where preliminary testing and final testing is
performed. All documents are signed between two parties and the
project is handed over to the customer.