- A New Process Required 13 Minutes To Produce The First Unit The Learning Rate Is 0 8 Round Your Answer To One Decimal P 1 (22.45 KiB) Viewed 46 times
A new process required 13 minutes to produce the first unit. The learning rate is 0.8 Round your answer to one decimal p
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
A new process required 13 minutes to produce the first unit. The learning rate is 0.8 Round your answer to one decimal p
A new process required 13 minutes to produce the first unit. The learning rate is 0.8 Round your answer to one decimal place. How long will it take (in minutes) to produce the 9th unit? minutes