9. After a significant redesign of the control station, you and the other safety engineers have requested the unit be re
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
9. After a significant redesign of the control station, you and the other safety engineers have requested the unit be re
9. After a significant redesign of the control station, you and the other safety engineers have requested the unit be re-tested. However, the test budget has been reduced in the past year. If you reduced the test hours to 800 and you want to ensure a failure rate (2) of less than 0.02 with 97.5% confidence, what is the maximum number of failures you can experience during the testing?