Assume that you are monitoring the center of a process but instead of using a standard 3-sigma chart you decide to set y
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Assume that you are monitoring the center of a process but instead of using a standard 3-sigma chart you decide to set y
Assume that you are monitoring the center of a process but instead of using a standard 3-sigma chart you decide to set your control limits at +/-3.3 standard deviations. Assuming the process remains stable: a. Would you expect to see more, less, or the same number of false alarms? a. Determine the expected run length for this chart (assuming the process is stable).