Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

7) Consider the following project: Initial outlay = $19 million Year 1 expected cash flow = $7 million Year 2 expected c

Post by answerhappygod »

7)
Consider the following project:
Initial outlay = $19 million
Year 1 expected cash flow = $7 million
Year 2 expected cash flow = $8 million
Year 3 expected cash flow = $10 million
Project cost of capital = 16.9%p.a.
The net present value of this project is closest to (in millions
to the nearest three decimals):
a.
$-0.898
b.
$-3.515
c.
$37.102
d.
$0.091