During an Oedometer test, a 10 mm thick soil sample completed 90% of consolidation for 5 minutes. Calculate the time for
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
During an Oedometer test, a 10 mm thick soil sample completed 90% of consolidation for 5 minutes. Calculate the time for
During an Oedometer test, a 10 mm thick soil sample completed 90% of consolidation for 5 minutes. Calculate the time for 90% consolidation for a 10 m thick layer (drainage is allowed only at the top) of the same clay: O 38 months 2000 minutes 38 years 7 years