Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion t

Post by answerhappygod »

Consider the following Activity-On-Node (AON) PERT project. The
three values that represent each activity's completion time (in
days) correspond to an optimistic time, most likely time, and
pessimistic time, respectively.




Refer to the figure. What deadline should be set to ensure a 99%
probability that the project will be completed within the deadline
date?