The following Activity on Arrow (AOA) network diagram shows the information about 4 different activities in a semester p
The following Activity on Arrow (AOA) network diagram shows the information about 4 different activities in a semester project 67 1,2 0,5 1,6 Os a. Determine the earliest start time for activity F b. If the latest time activities E and F are to be finished is 13, determine the latest finish time for activity C Latest frish time c. What is the slack for each activity? Activity Slack C D E F