A company is deciding how to invest £8 million between three different projects. For each project, investment can be at
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
A company is deciding how to invest £8 million between three different projects. For each project, investment can be at
company is deciding how to invest £8 million between three different projects. For each project, investment can be at different levels as stated in the following table. All values are given in thillions of pounds. Project 1 Project 2 Project 3 Proposal Investment Revenue Investment Revenue Investment Revenue 1 5 1 3 1 2 3 8 2 6 2 7 3 4 10 3 8 4 9 The company require that at least £1 million must be invested in each project. Use dynamic programming to find the investment in each project that maximises the to- tal revenue. State all optimal solutions and include all definitions. No marks will be awarded if a method other than dynamic programming is used. [25] 123 2