The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Tim
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Tim
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) Activity b A B 10 C D E 15 Table 9.2 Reference: Ref 9-2 Using Table 9.2, the expected time to complete the project is Select one: OA. 21.67 weeks. B. 34.17 weeks. C. 33.23 weeks. D. 31.00 weeks. 3 GINA W 4 2 6 5 3 L 0039 525 12 Activity Predecessor -- A A B, C D
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!