The following table of probabilistic time estimates (in weeks)
and activity predecessors are provided for a project.
Time Estimates (weeks)
Activity
a
m
b
Activity Predecessor
A
3
5
7
--
B
4
8
10
A
C
2
3
5
A
D
6
9
12
B, C
E
5
9
15
D
Table 9.2
Reference: Ref 9-2
Using Table 9.2, the probability that the project could be
completed in 34 weeks or less is approximately
Select one:
A.
0.96.
B.
0.86.
C.
0.89.
D.
0.91.