A job was budgeted to require 6 hours of labor per unit at $10.00 per hour. The job consisted of 6,800 units and was completed in 37,800 hours at a total labor cost of $410,400. What is the direct labor efficiency variance? Multiple Choice $32,400 unfavorable. $32,400 favorable. $30,000 unfavorable. $30,000 favorable. $2,400 unfavorable.