4. For the project described in the table below, show, step by step, how to reduce its duration. Activity times are in d
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
4. For the project described in the table below, show, step by step, how to reduce its duration. Activity times are in d
4. For the project described in the table below, show, step by step, how to reduce its duration. Activity times are in days. Indirect project cost is $2,000 per day. What is the optimal duration of the project? Daily Crash Activity Normal Time Crash Time: Cost 2-3 7 5 $700 2-4 8 7 $1,500 3-5 6 5 $1,000 4-7 11 8 $1,700 4-6 4 3 $500