Question: A project precedence table with normal and crash times and cost is given in tables: Activity Predecessor Norma

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Question: A project precedence table with normal and crash times and cost is given in tables: Activity Predecessor Norma

Post by answerhappygod »

Question A Project Precedence Table With Normal And Crash Times And Cost Is Given In Tables Activity Predecessor Norma 1
Question A Project Precedence Table With Normal And Crash Times And Cost Is Given In Tables Activity Predecessor Norma 1 (94.39 KiB) Viewed 19 times
Question: A project precedence table with normal and crash times and cost is given in tables: Activity Predecessor Normal Time Crash Normal Maxi Crash Cost (Weeks) Times Cost mum (Week (RS.) (Rs) Crash s) 4 2 8000 9000 - 1 A 5 2 16000 20000 2 A 4 1 12000 13000 1 B,C 6 4 34000 35000 2 A 6 4 42000 44000 2 E 5 3 16000 16500 1 D,F 7 4 66000 72000 3 G,D 4 2 2000 5000 1 1) Draw the network diagram and critical path tables (show status of critical path) for the above mentioned table scenario. . Tell the latest start time for Activity D,G,H before and after crashing ● Tell the earliest start time for activity A,B,C,E before and after crashing 2) Determine a crashing scheme for the above project to answer the following questions: o Find the cost needed to reduce total project duration by 3 weeks O Find the maximum crash time this project can get (in months) O Tell how much we can crash the project time if we have budget of Rs. 5000 o Tell how much we can crash the project time if we have budget between 5000 and 1000 O Tell how much project's budget increase (in percentage) in case of maximum crash time. O Find the total crash cost for maximum crash time O Tell how much we can crash the project if client agree to increase budget of project by $100 ABCDEFGH
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!
Post Reply