Budget Account Code Quantity Total 4,000 03110 Formwork 03210 Rebar 10 800 03310 Place & Finish Subtotal Slabs at grade

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Budget Account Code Quantity Total 4,000 03110 Formwork 03210 Rebar 10 800 03310 Place & Finish Subtotal Slabs at grade

Post by answerhappygod »

Budget Account Code Quantity Total 4 000 03110 Formwork 03210 Rebar 10 800 03310 Place Finish Subtotal Slabs At Grade 1
Budget Account Code Quantity Total 4 000 03110 Formwork 03210 Rebar 10 800 03310 Place Finish Subtotal Slabs At Grade 1 (101.89 KiB) Viewed 14 times
-what is the percent complete for accounts 03110, 03210 and 03310
Budget Account Code Quantity Total 4,000 03110 Formwork 03210 Rebar 10 800 03310 Place & Finish Subtotal Slabs at grade O a. 75 percent, 60 percent, 80 percent. O b. 75 percent, 63 percent, 85 percent. OC 73 percent, 60 percent, 86 percent. O d. 70 percent, 65 percent, 80 percent. UOM SF Ton CY Actual Quantity To-Date 3,000 6 640 Budget PV 6,000 900 800 Eamed Percent EV Complete E C Time left 0:19:04