QUESTION 12 Assume that there are : o 3 processes P1, P2. & P3 • 3 Resources Ri( two instances), R2 (one instance), & R3
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
QUESTION 12 Assume that there are : o 3 processes P1, P2. & P3 • 3 Resources Ri( two instances), R2 (one instance), & R3
QUESTION 12 Assume that there are : o 3 processes P1, P2. & P3 • 3 Resources Ri( two instances), R2 (one instance), & R3 (two instances) And the processes make the requests for resources in the following order: o Pl requests R1 o P2 requests R2 • P1 requests R2 o P3 request R3 o P3 Request R2 - P2 request R3 Draw the resource allocation graph and find whether deadlock exists? Justify your answer.