Clues: 1- The time unit is weeks 2- Durations are: 1, 2, 3, 4, 5, 6, 7. 3- No two activities have the same duration. 4-

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Clues: 1- The time unit is weeks 2- Durations are: 1, 2, 3, 4, 5, 6, 7. 3- No two activities have the same duration. 4-

Post by answerhappygod »

Clues 1 The Time Unit Is Weeks 2 Durations Are 1 2 3 4 5 6 7 3 No Two Activities Have The Same Duration 4 1
Clues 1 The Time Unit Is Weeks 2 Durations Are 1 2 3 4 5 6 7 3 No Two Activities Have The Same Duration 4 1 (248.56 KiB) Viewed 9 times
Clues 1 The Time Unit Is Weeks 2 Durations Are 1 2 3 4 5 6 7 3 No Two Activities Have The Same Duration 4 2
Clues 1 The Time Unit Is Weeks 2 Durations Are 1 2 3 4 5 6 7 3 No Two Activities Have The Same Duration 4 2 (362 KiB) Viewed 9 times
Clues:
1- The time unit is weeks
2- Durations are: 1, 2, 3, 4, 5, 6, 7.
3- No two activities have the same duration.
4- There exists only one critical path, and it is the largest possible number given the possible durations shown.
5- The slack times of the seven activities are: 0, 0, 0, 3, 6, 8, 8
6- Activity E has the smallest amount of slack that is greater than zero.
7- The early finish (EF) time for activity A is four weeks, and this does not equal the latest finish (LF) time. (Note: There is no negative slack in the network.)
8- The slack in activity C is eight weeks.
9- The duration of activity F is greater than the duration of activity C by at least two weeks.
Requirements: 1. For each activity calculate: ES, EF, Duration, LS, LF, and Slack. 2. This assignment can be done in a group of four. 3. Make a PowerPoint with animation and explanation to show how you solved the puzzle.
Puzzle: A project manager discovers that his team has neglected to complete the network diagram for the project. The network diagram is shown below. B D START A E G END C I