Construct A Precedence Diagram 1 (44.87 KiB) Viewed 20 times
a) Given in the following table are the task necessary for the assembly of Fine Cedar Chest, the length of time needed to perform each task, and the operations that must be completed prior to subsequent operations. Work Element Precedence Time (min) A None 2 B A 4 с B 5 None D None F C, E, G DEE D F GI G H 531 2 4