Parte Question 2: (Mark 6] The following general activities are proposed for production of heavy machines (not in order)
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Parte Question 2: (Mark 6] The following general activities are proposed for production of heavy machines (not in order)
Parte Question 2: (Mark 6] The following general activities are proposed for production of heavy machines (not in order) Test of prototype (3 weeks) Revise the design (2 weeks) Pre-Design (4 weeks) Market analysis (2 weeks) Order of raw materials (5 weeks) Construction of Prototype (3 weeks) Production of machines (4 weeks) Construct the GANTT chart for this process in the correct order of activities and define the critical path for it. Note: Some activities are parallel. . .