- 4 For Construction Of An Embankment The Specifications Require 95 Relative Compaction At The Optimum Water Content La 1 (11.64 KiB) Viewed 24 times
4. For construction of an embankment the specifications require 95% relative compaction at the optimum water content. La
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
4. For construction of an embankment the specifications require 95% relative compaction at the optimum water content. La
4. For construction of an embankment the specifications require 95% relative compaction at the optimum water content. Laboratory testing of the embankment soil revealed a maximum dry density of 18 kN/m'at 12% water content. Determine the required minimum field dry density and water content.