A project requires $150 million investment. If you invest today, the present value of future cash flow is worth $180 mil

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

A project requires $150 million investment. If you invest today, the present value of future cash flow is worth $180 mil

Post by answerhappygod »

A project requires $150 million investment. If you
invest today, the present value of future cash flow is worth $180
million. You can wait for one year to observe the demand of the
market; however, you forgo the cashflow in year 1. Assume if the
demand is high, there will be a cash flow of $22 million in year 1
and the present value of future cash flows at the end of year 1 is
$220 million; if the demand is low, there will be a cash flow of
$12 million in year 1 and the present value of future cash flows at
the end of year 1 is $120 million. You need to use risk-neutral
valuation method to decide either invest today and start to collect
the cash flow or delay it for one year. Annual risk-free rate is
3%. Show your work to get full credit. Keep four
decimals.
(a). What’s the risk-neutral probability of high
demand?
(b). What’s the value of the timing
option?
(c). Do you want to wait for one year or invest today?
Why?